"主体变化 (2)"
"变 化 调 度"
"2010年8月3日"
"专业分类","单位","级别",,"变化地点","变化性质","变化时间","变化内容","管理措施","四点班","零点班","八点班"
"生产变化","王庄煤矿","二级",,"52/2#综采面","关键层来压","8月2日","8月2日至8月5日期间,即52/2#工作面推进至70-85米时,机头段顶板关键层开始断裂显现并逐渐向机尾延伸.","1,严格执行52/2#面回采作业规程及关键层来压专项措施;2,加强来压期间的瓦斯,水,顶板管理;3,加强设备检修;4,加强矿压预测预报;5,加强两端头超前维护."
,"漳村煤矿","三级",,"2305面","安装","8月2日","完善,调试.","执行安装规程"
,"常村煤矿","三级",,"S5-8工作面","回撤","8月2日8点班","当日回9组中间架;累计完成回撤电气列车,转载机,破碎机,皮带,前后溜,75组架.","1,队组执行了《S5-8工作面回撤安全技术措施》2,回撤期间安排生产科,机电科,通风科,运输科,安监科跟班指挥作业"
,,"三级",,"S5-3工作面","安装","8月2日8点班","当日安9组中间架;累计对前溜120节,后溜(剩机尾未安装),66组架.","1,队组执行《S5-3工作面安装安全技术措施》2,安装期间安排机电科,电力科,自动化,通风科,运输科等科室三天到位巡查一次"
,"余吾煤业","三级",,"N1203工作面","安装","8月2日","圆班拖高压管35根,瓦排巷打木垛3个,回顺架超前支护10排.","专项措施"
,,"三级",,"S2106工作面","安装","8月2日","圆班下支架8组,安装支架12组,累计下支架45组,安装支架37组,上转载机刮板7块,卸料3车,安装连接头12个,安装后溜千斤顶8个.","专项措施"
"地质变化","余吾煤业有限责任公司","三级",,"S2205工作面","底板","8月2日","S2205工作面回采至721米时,遇到F119断层,圆班推进3.2m.累计过25.6m,约剩余28.2m.","专项措施"
,"潞宁煤业公司","三级",,"22111工作面","冲刷构造","8月2日","工作面26#架—31#架,43#架—50#架过冲刷构造.","已制定专项措施防范"
,"夏店煤矿","二级",,"3103回风巷","排放水","8月2日","正常排放水,20方/小时.","有排放水专项管理措施"
"机电变化","石圪节煤业公司","二级",,"15102风运巷 15106风运巷","停电","8月3日 17:00-19:00","摇测15102风,运巷,15106风巷,运巷高压线路绝缘.","严格执行两票制度"
,"郭庄煤矿","一级"," ","屯留局110kv变电站","单回路运行","8月1日—8月6日","屯郭451线停电,库郭427线单回路运行,继续更换进线开关.","严格执行35kv线路单回路运行措施"
"通风变化","常村煤矿","三级",,"S6-2尾巷","立交","8月2日8点班","当日掘进1米,破底1.2米,套棚3架;累计套棚19架;目前已施工立交3.5米;剩余1米过完立交.","1,队组执行《S6-2尾巷掘进安全技术措施》2,过立交期间安排生产科,通风科,地测科,安监科跟班指挥作业"
,"余吾煤业","三级","√","S1206瓦排巷反掘段","贯通","8月2日","圆班掘进5.4m,剩余1.8m,当日18:55,与南翼胶带大巷贯通.","专项措施"
,"高河能源公司","三级"," ","中央风井主通风机","正常切换","8月3日","当日9时,中央风井主通风机由1#运行切换至2#运行.","执行《中央风井主通风机切换安全技术措施》"
,"郭庄煤矿","三级",,"中央变电所延伸段","贯通","8月2日","截止今日八点班中央变电所延伸段与中央变电所剩余2.8米贯通(不包括壁厚及壁厚空隙).","严格执行贯通安全技术措施"
,,"三级",,"3313皮顺回风巷","贯通","8月2日","截止今日八点班3313皮顺回风巷与三采区回风巷剩余14米贯通.","严格执行贯通安全技术措施"
"综合变化","漳村煤矿","二级",,"13采区","排水","8月2日","水位观测,根据水位情况开泵排水.","执行安全技术措施"
,"煤基合成油","一级"," ","全厂","检修","8月2日","1,热动车间1#,2#,4#锅炉运行,负荷400T/h;2,气化车间2#,3#,4#气化炉运行;氧负荷11500NM3/h;3,净化车间A,B套空分正常运行,低温甲醇洗,氨吸收制冷,甲烷转化,变压吸附各工段运行;4,合成车间2#费托工段运行, 2日 12:13 油品加工工段投H2气开车;1日20:02 合成还原工段开始升温;5,尿素合成氨运行,尿素主框架升温钝化;6,8月1日16:00到8月2日16:00 尿素产品:20.5 T."
"供电变化","司马煤业公司","二级"," ","35KV变电所","供电回路单回路供电","8月3日","从8月3日上午6时开始,对公司城南供电路线412停电并拆除,同时将苏司供电线路二回路388接入公司35KV变电站内,预计8月4日下午18时苏司供电线路二回路388送电(形成双回路供电系统),其间我公司供电系统单回路运行.","严格按《35KV变电站单回路运行安全技术措施》执行."
,,"二级","√","苏店二回路—原城南321进线","接地,对调","8月2日 8:00—20:30","苏店二回路—原城南321进线进行保护接线对调."
,"常村煤矿","三级",,"S6皮带机头变电所","单回路运行"," 8月2日 19:10- ","西坡6KV高压室605柜停电接S6采区临时变电所电源(I段),停电期间S6皮带机头变电所单回路运行.","1,已制定专项安全技术措施"
,"高河能源公司","三级"," ","南翼进风大巷,南翼东回风大巷风机","单回路供电","8月3日 9:00—11:00","拆除小庄进风井底原南翼进风大巷,南翼东回风大巷风机Ⅱ回路变压器,南翼进风大巷,南翼东回风大巷风机Ⅱ回路电源停电,期间南翼进风大巷,南翼东回风大巷风机为单回路供电.","执行《井下局扇单回路供电安全技术措施》"
,,"三级","√","E1302回风顺槽,瓦排巷风机","单回路供电","8月2日 11:59—13:56","E1302回风顺槽,瓦排巷风机Ⅱ回路开关检修完毕,E1302回风顺槽,瓦排巷风机Ⅱ回路电源停电结束,E1302回风顺槽,瓦排巷风机恢复双回路供电.","执行《井下局扇单回路供电安全技术措施》"
,,"三级"," ","E1302辅运顺槽, 胶带顺槽风机","单回路供电","8月3日 12:00—14:00","检修E1302辅运顺槽,胶带顺槽风机Ⅰ回路,E1302辅运顺槽,胶带顺槽风机Ⅰ回路电源停电,期间E1302辅运顺槽,胶带顺槽风机为单回路供电.","执行《井下局扇单回路供电安全技术措施》"
"备注: 1,无变化内容的矿井有李村矿井筹备处,五阳煤矿,慈林山煤矿."
" 2,"√"为已完成的变化项目;" "为当日需重点关注的变化项目."
"整合下井"
"潞安矿业集团公司整合矿井矿级领导每日下井情况统计表"
"2010年8月2日"
"主体","整合","职务","姓名","下井时间","下井地点"
"矿井","矿井"
"集团公司","华润煤业","矿长助理","胡志华","零点班","3部皮带,203运回巷,202工作面"
,,"生产助理","史文俊","四点班","3部皮带,203运回巷,202工作面"
,,"机电矿长","刘顺才","八点班","3部皮带,203运回巷,202工作面"
,"常兴煤业","总经理","高路","八点班","松树岭矿"
,,"安全经理","党泽亮","八点班","2104工作面,2106回风巷,2106运输巷,三采区回风巷"
,,"机电经理","暴瑞卿","四点班","松树岭矿"
,,"通风经理","蒋成瑞","四点班","2104工作面,2106回风巷,2106运输巷,三采区回风巷"
"漳村煤矿","后堡煤业","安全经理","张崇嵘","八点班","201采区"
,,"通风经理","牛金明","四点班","201采区"
,,"总工程师","侯超","零点班","201采区"
,"和顺一缘 煤业","总工程师","林晋彬","零点班","材料下山工作面"
,,"通风经理","曹宇","八点班","150103综采工作面"
,,"生产经理","张光明","四点班","150109下顺槽掘进工作面"
,"上庄煤矿","总经理","刘建宏","八点班","3103工作面"
"王庄煤矿","黑龙煤业","生产矿长","马保明","八点班","主副斜井"
,,"通风矿长","武文庆","四点班","主副斜井"
"常村煤矿","瑞龙煤业","矿长","张书玉","八点班","裕民矿二采区轨道下山,中央水仓"
,"祥升煤业","矿长","孙金亮","八点班","一二水平工作面"
,"长喻河煤业","生产矿长","田和平","八点班","正泰矿区080406上工作面"
,"麦捷煤业","通风矿长","李天晴","四点班","15#上总回"
,,"安全矿长","任国强","八点班","311轨顺"
,"温庄煤业","矿长","梁建军","四点班","150301综采工作面和中央变电所"
,,"机电矿长","范燕飞","零点班","150301综采工作面和瓦斯泵站"
,,"安全矿长","郭李刚","八点班","150301综采工作面和主井底"
"司马煤业公司","左权佳瑞 煤业公司","通风经理","赵晓宇","四点班","主斜井1#措施巷,主斜井1#措施巷"
,,"安全经理","苏连生","八点班","轨道大巷工作面,轨道大巷工作面"
,"阜生煤业","安全经理","李晋恒","八点班","井下各地点"
,"五里堠煤业","总工程师","王 刚","八点班","副井,030210工作面"
,,"机电经理","刘建中","零点班","主井,集中轨运下山"
,,"总经理","苗润田","四点班","副井,030210工作面"
"郭庄煤矿","小南村煤业","生产矿长","王有成","四点班","1#水仓"
,,"安全矿长","赵双龙","八点班","1#水仓"
,"东盛煤业","机电矿长","秦正平","四点班","变电所通道"
,,"生产矿长","王双生","八点班","集中皮带巷"
"整合变化"
"集团公司整合矿井变化调度分级管理汇总表"
"2010年8月3日"
"专业分类","主体矿井","整合矿井","级别",,"变化地点","变化性质","变化时间","变化内容","管理措施"
"生产变化","集团公司","华润煤业公司","三级"," ","203运输顺槽","与空巷贯通","8月2日","当日6:30,203运输顺槽掘进中与空巷贯通(空巷情况:距贯通点长14米,高6.5米,距左帮9米,距右帮不清楚).","停工,研究过空方案."
,"王庄煤矿","伊田煤业","三级",,"山中(过渡矿井)3#皮带巷","有计划修巷","8月2日","扩帮8米.","《3#皮带巷修巷安全技术措施》"
,,,"三级",,"山中(过渡矿井)北辅皮巷","有计划修巷","8月2日","架棚3架.","《北辅皮巷修巷安全技术措施》"
,,,"三级",,"红道(关闭矿井)集中运输巷","巷道加固","8月2日","架棚3架.","《集中运输巷修巷安全技术措施》"
,,"黑龙煤业","三级",,"主井","掘进","8月2日","主井掘进1.3M.","严格执行《主井管理措施》"
,,,"三级",,"副井","掘进","8月2日","副井掘进1.5M.","严格执行《副进管理措施》"
,"漳村煤矿","后堡煤业","三级",,"201采区回风巷","有计划修巷","8月2日","局部巷道挑顶,拉底,铺设轨道.","执行安全技术措施"
,,"和顺一缘煤业","三级",,"专用回风下山","巷道改造","8月2日","由原锚网支护变为料石砌碹.","严格按专用回风下山砌碹措施执行"
,"常村煤矿","温庄煤业","三级",,"150301综采工作面","推进","8月1日4点班至 8月2日8点班","8月1日4点班割煤2刀,8月2日0点班割煤2刀,8月2日8点班检修,空巷位置在21架至23架.","1,正常执行《150301综采工作面回采作业规程》.2,安全指挥中心监督规程的执行情况.3,严格执行领导干部现场跟班制度."
,,,"三级",,"1504皮带巷","准备掘进","8月1日4点班至 8月2日8点班","8月1日4点班至8月2日8点班掘进一队在1504皮带巷做掘进准备工作.","1,已编制《1504皮带巷掘进安全技术措施》"
,,,"三级",,"19#贯眼","掘进","8月2日8点班","19#贯眼掘进4排3.6米,累计掘进14.4米.","1,已编制《19#贯眼掘进安全技术措施》"
,,"昌泰煤业","三级",,"090502回风巷","开工","8月3日0点班","090502回风巷开始掘进.","1,已编制《090502掘进工作面作业规程》.2,矿领导现场跟班."
,,"长喻河煤业","三级",,"正泰矿区080406上工作面","回撤","8月2日","正泰矿区080406上工作面出架4组,装车上井3组.","1,严格按照《080406上综采工作面回撤作业规程》执行.2,矿领导现场跟班."
"地质变化","漳村煤矿","开拓煤业","二级",,"2102材料巷","探放水","8月2日","2102开口处以30度角方位打钻23米,正常.","已制定安全技术措施"
,,,"二级",,"2106运巷探水巷","探放水","8月2日","2106运巷探水巷左邦打钻18米见岩石.","已制定安全技术措施"
,"常村煤矿","长喻河煤业","二级",,"正泰矿区1502运输巷","探放水","8月3日","正泰矿区1502运输巷由于25#钻孔封堵情况不确定,停止掘进,焦作理工大学专家已进行了二次勘探,现勘探报告已出来,8月4日准备在总回风巷打测压钻孔,现做准备工作.","严格按照《总回风巷探放水安全技术措施》执行."
,,"麦捷煤业","三级",,"310工作面","揭露小型地质构造","8月3日","310综采工作面68#架至84#架过褶曲构造,底板隆起最高处1.8米,最低0.2米.","1,严格按照《150310工作面过地质构造安全技术措施》执行."
"机电变化","漳村煤矿","开拓煤业","二级",,"全矿","停电","8月2日 7:06—20:00","蒲县电业局通知对860,862两趟线路改造需停电.停电后,启动柴油发电机,保障矿井保安电源.","启动大面积停电应急预案"
,"常村煤矿","温庄煤业","三级","√","瓦斯泵站","检修","8月2日 9:00—11:54","瓦斯泵站停泵检修."
"监测监控","漳村煤矿","上庄煤矿","三级",,"井下探头","断电试验","8月3日 8:00—16:00","全矿各作业地点做甲烷传感器断电试验调校.","保证断电试验数据准确"
"供电变化","司马煤业公司","左权佳瑞煤业公司","二级","√","公司","单回路运行","8月1日9:21— 8月2日7:50","8月2日7:50,左其专线正常供电,恢复双回路供电.","《矿井大面积停电事故应急预案》"
,,"阜生煤业","二级","√","全矿井","单回路运行","8月2日","当日7:50,左其专线正常供电,恢复双回路供电.","严格按单回路管理措施执行"
"备注: 1,无变化内容的矿井有五里堠煤业,祥升煤业,瑞龙煤业,安吉煤业,金鑫城煤业,小南村煤业."
" 2,"√"为已完成的变化项目;" "为当日需重点关注的变化项目."
"主体变化"
"集团公司变化调度分级管理汇总表"
"2010年8月3日"
"专业分类","单位","级别",,"变化地点","变化性质","变化时间","变化内容","管理措施"
"生产变化","王庄煤矿","二级",,"52/2#综采面","关键层来压","8月2日","8月2日至8月5日期间,即52/2#工作面推进至70-85米时,机头段顶板关键层开始断裂显现并逐渐向机尾延伸.","1,严格执行52/2#面回采作业规程及关键层来压专项措施;2,加强来压期间的瓦斯,水,顶板管理;3,加强设备检修;4,加强矿压预测预报;5,加强两端头超前维护."
,"漳村煤矿","三级",,"2305面","安装","8月2日","完善,调试.","执行安装规程"
,"常村煤矿","三级",,"S5-8工作面","回撤","8月2日8点班","当日回9组中间架;累计完成回撤电气列车,转载机,破碎机,皮带,前后溜,75组架.","1,队组执行了《S5-8工作面回撤安全技术措施》2,回撤期间安排生产科,机电科,通风科,运输科,安监科跟班指挥作业"
,,"三级",,"S5-3工作面","安装","8月2日8点班","当日安9组中间架;累计对前溜120节,后溜(剩机尾未安装),66组架.","1,队组执行《S5-3工作面安装安全技术措施》2,安装期间安排机电科,电力科,自动化,通风科,运输科等科室三天到位巡查一次"
,"余吾煤业","三级",,"N1203工作面","安装","8月2日","圆班拖高压管35根,瓦排巷打木垛3个,回顺架超前支护10排.","专项措施"
,,"三级",,"S2106工作面","安装","8月2日","圆班下支架8组,安装支架12组,累计下支架45组,安装支架37组,上转载机刮板7块,卸料3车,安装连接头12个,安装后溜千斤顶8个.","专项措施"
"地质变化","余吾煤业","三级",,"S2205工作面","底板","8月2日","S2205工作面回采至721米时,遇到F119断层,圆班推进3.2m.累计过25.6m,约剩余28.2m.","专项措施"
,"潞宁煤业公司","三级",,"22111工作面","冲刷构造","8月2日","工作面26#架—31#架,43#架—50#架过冲刷构造.","已制定专项措施防范"
,"夏店煤矿","二级",,"3103回风巷","排放水","8月2日","正常排放水,20方/小时.","有排放水专项管理措施"
"机电变化","石圪节煤业公司","二级",,"15102风运巷 15106风运巷","停电","8月3日 17:00-19:00","摇测15102风,运巷,15106风巷,运巷高压线路绝缘.","严格执行两票制度"
,"郭庄煤矿","一级"," ","屯留局110kv变电站","单回路运行","8月1日—8月6日","屯郭451线停电,库郭427线单回路运行,继续更换进线开关.","严格执行35kv线路单回路运行措施"
"通风变化","常村煤矿","三级",,"S6-2尾巷","立交","8月2日8点班","当日掘进1米,破底1.2米,套棚3架;累计套棚19架;目前已施工立交3.5米;剩余1米过完立交.","1,队组执行《S6-2尾巷掘进安全技术措施》2,过立交期间安排生产科,通风科,地测科,安监科跟班指挥作业"
,"余吾煤业","三级","√","S1206瓦排巷反掘段","贯通","8月2日","圆班掘进5.4m,剩余1.8m,当日18:55,与南翼胶带大巷贯通.","专项措施"
,"高河能源公司","三级"," ","中央风井主通风机","正常切换","8月3日","当日9时,中央风井主通风机由1#运行切换至2#运行.","执行《中央风井主通风机切换安全技术措施》"
,"郭庄煤矿","三级",,"中央变电所延伸段","贯通","8月2日","截止今日八点班中央变电所延伸段与中央变电所剩余2.8米贯通(不包括壁厚及壁厚空隙).","严格执行贯通安全技术措施"
,,"三级",,"3313皮顺回风巷","贯通","8月2日","截止今日八点班3313皮顺回风巷与三采区回风巷剩余14米贯通.","严格执行贯通安全技术措施"
"综合变化","漳村煤矿","二级",,"13采区","排水","8月2日","水位观测,根据水位情况开泵排水.","执行安全技术措施"
,"煤基合成油","一级"," ","全厂","检修","8月2日","1,热动车间1#,2#,4#锅炉运行,负荷400T/h;2,气化车间2#,3#,4#气化炉运行;氧负荷11500NM3/h;3,净化车间A,B套空分正常运行,低温甲醇洗,氨吸收制冷,甲烷转化,变压吸附各工段运行;4,合成车间2#费托工段运行, 2日 12:13 油品加工工段投H2气开车;1日20:02 合成还原工段开始升温;5,尿素合成氨运行,尿素主框架升温钝化;6,8月1日16:00到8月2日16:00 尿素产品:20.5 T."
"供电变化","司马煤业公司","二级"," ","35KV变电所","供电回路单回路供电","8月3日","从8月3日上午6时开始,对公司城南供电路线412停电并拆除,同时将苏司供电线路二回路388接入公司35KV变电站内,预计8月4日下午18时苏司供电线路二回路388送电(形成双回路供电系统),其间我公司供电系统单回路运行.","严格按《35KV变电站单回路运行安全技术措施》执行."
,,"二级","√","苏店二回路—原城南321进线","接地,对调","8月2日 8:00—20:30","苏店二回路—原城南321进线进行保护接线对调."
,"常村煤矿","三级",,"S6皮带机头变电所","单回路运行"," 8月2日 19:10- ","西坡6KV高压室605柜停电接S6采区临时变电所电源(I段),停电期间S6皮带机头变电所单回路运行.","1,已制定专项安全技术措施"
,"高河能源公司","三级"," ","南翼进风大巷,南翼东回风大巷风机","单回路供电","8月3日 9:00—11:00","拆除小庄进风井底原南翼进风大巷,南翼东回风大巷风机Ⅱ回路变压器,南翼进风大巷,南翼东回风大巷风机Ⅱ回路电源停电,期间南翼进风大巷,南翼东回风大巷风机为单回路供电.","执行《井下局扇单回路供电安全技术措施》"
,,"三级","√","E1302回风顺槽,瓦排巷风机","单回路供电","8月2日 11:59—13:56","E1302回风顺槽,瓦排巷风机Ⅱ回路开关检修完毕,E1302回风顺槽,瓦排巷风机Ⅱ回路电源停电结束,E1302回风顺槽,瓦排巷风机恢复双回路供电.","执行《井下局扇单回路供电安全技术措施》"
,,"三级"," ","E1302辅运顺槽, 胶带顺槽风机","单回路供电","8月3日 12:00—14:00","检修E1302辅运顺槽,胶带顺槽风机Ⅰ回路,E1302辅运顺槽,胶带顺槽风机Ⅰ回路电源停电,期间E1302辅运顺槽,胶带顺槽风机为单回路供电.","执行《井下局扇单回路供电安全技术措施》"
"备注: 1,无变化内容的矿井有李村矿井筹备处,五阳煤矿,慈林山煤矿."
" 2,"√"为已完成的变化项目;" "为当日需重点关注的变化项目."
"Sheet1"
"潞安矿业集团公司副处级以上领导每日下井情况统计表 "
"2010年8月2日"
"单位","姓名","下井时间","下井地点","备注"
"公司领导","刘克功","四点班","常村矿N3-7轨顺"
"生产处","修成智","四点班","常村矿N3-7轨顺"
"地质处","刘保金","四点班","常村矿N3-7轨顺"
"机电处","王昕","四点班","常村矿N3-7轨顺"
"总工办","宋献忠","四点班","常村矿N3-7轨顺"
"主体下井"
"潞安矿业集团公司各矿矿级领导每日下井情况统计表"
"2010年8月2日"
"单位","职务","姓名","下井时间","下井地点"
"石圪节煤业公司","生产副总经理","郭民俭","四点班","2129风云巷"
,"机电副总经理","呼世杰","八点班","材料斜井"
"五阳煤矿","机电矿长","靳志强","八点班","7600工作面"
"漳村煤矿","经营矿长","冯瑞波","零点班","西下山CST"
,"后勤矿长","史根保","零点班","2502风运巷"
"王庄煤矿","矿长","肖亚宁","零点班","71辅助运输巷"
,"总工程师","杨建立","四点班","52/2#面"
,"安全矿长","张日林","四点班","52/2#面"
"常村煤矿","纪委书记","李明书","四点班","N3-3轨顺"
,"生产矿长","张国庆","零点班","S3-9工作面"
"司马煤业公司","安全矿长","程润明","八点班","1113措施巷"
"余吾煤业有限责任公司","总工程师","霍灵军","八点班","S2206胶带顺槽,S2106工作面"
,"生产副总经理","崔树江","零点班","N1203工作面"
,"经营副总经理","闫波","零点班","S1206瓦排巷"
"郭庄煤矿","财务副总经理","李瑞生","零点班","1306工作面"
,"洗煤副总经理","姬香山","四点班","1306工作面"
"潞宁煤业公司","董事长","杨新建","四点班","22103风巷"
,"生产副总经理","王中青","八点班","3#石门联巷"
,"安全副总经理","刘小峰","零点班","3#石门联巷"
,"机电副总经理","牛文斌","零点班","22103风巷"
,"经营副总经理","左君武","四点班","西扩区皮带巷"
,"基建副总经理","王玺","八点班","西扩区皮带巷"
"慈林山煤矿","生产矿长","王建虎","八点班","下组煤"
,"机电矿长","曹安顺","八点班","下组煤"
,"通风矿长","张咏斌","零点班","下组煤"
,"纪委书记","赵五虎","四点班","下组煤"
"夏店煤矿","矿长","董经存","八点班","3106工作面"
,"党委书记","李志华","八点班","3111工作面"
,"总工程师","梁树平","零点班","3508工作面"
,"安全矿长","段吉祥","八点班","3106工作面"
,"销售矿长","贾会勇","四点班","3111工作面"
"高河能源公司","执行副总裁","宇黎亮","零点班","E1302回风顺槽"
,"安全经理","常安明","八点班","南翼辅运大巷"
,"机电经理","梁玉田","四点班","南翼东回风大巷"
,"财务总监","王卫","零点班","E1302回风顺槽"
- 掘进工作面作业规程 > "主体变化
-
"主体变化
下载该文档 文档格式:XLS 更新时间:2010-08-02 下载次数:0 点击次数:19文档基本属性 文档语言: Simplified Chinese 文档格式: xls 文档作者: 关键词: 主题: 备注: 点击这里显示更多文档属性 经理: 单位: 分类: 创建时间: 2010-08-02 13:27:33 上次保存者: 修订次数: 编辑时间: 文档创建者: 修订: 加密标识: 幻灯片: 段落数: 字节数: 备注: 演示格式: 上次保存时间:
- 下载地址 (推荐使用迅雷下载地址,速度快,支持断点续传)
- XLS格式下载
- 更多文档...
-
上一篇:淮南煤矿安全监察简报
下一篇:采区巷道方案设计
点击查看更多关于掘进工作面作业规程的相关文档
- 您可能感兴趣的
- 掘进作业规程 运输下山掘进作业规程 巷道掘进作业规程 下山掘进作业规程下载 恩洪煤矿掘进作业规程 岩巷掘进作业规程 井巷锚喷掘进作业规程 煤矿石门掘进作业规程 高抽巷掘进作业规程
- 大家在找
-
- · 造价工程师历年试题
- · 起名字男孩兔年
- · 一夜交友网qq群号
- · 2020dnf.绝杀官网
- · 下载《电力电子技术基础》
- · 奥迪q7汽车图片
- · tqyb天气预报z
- · 医疗安全教育课件
- · 机修钳工实习报告
- · 北京丰田汽车4s店
- · vb6.0中文版下载
- · 沁园春·雪课堂实录
- · ppt消费者行为案例
- · dlink无线路由器设置
- · 应聘会计助理面试技巧
- · 52pk单机游戏下载中心
- · 香港旺角购物
- · aaaa西服
- · 浙江开山集团董事长
- · 其他业务成本会计分录
- · 论文引述标注
- · 汽车离合器
- · 直流电变交流电
- · 血液灌流治疗重症药疹
- · 北师大版初中数学习题
- · 九年级上册物理课后题
- · 黑龙江省绥芬河市
- · 长江钢琴质量怎么样
- · 巴士驾驶员2010win7
- · ananwg.com破军
- · 交换机的作用
- · 北京事件6.4
- · 合肥监狱公务员待遇
- · 春晚后李咏朱军对骂
- · 马鞍山市人力资源和社会保障
- · 3g.youku.com
- · 经济数学基础形成性考核册
- · 武林风2011年9月10日
- · 迅驰基金传销
- · 教育学考研各专业简介
- 赞助商链接